<?xml version="1.0" encoding="UTF-8"?><rss xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:content="http://purl.org/rss/1.0/modules/content/" xmlns:atom="http://www.w3.org/2005/Atom" version="2.0"><channel><title><![CDATA[Working days, weekends, and working hours in GanttPRO]]></title><description><![CDATA[<p dir="auto">How can I change working days and weekends in GanttPRO?</p>
<p dir="auto">We don’t necessarily work from Monday to Friday, so I need the schedule to reflect Saturdays, Sundays, or different working hours. Please let me know how we can customize the working week.</p>
]]></description><link>https://community.ganttpro.com/topic/103/working-days-weekends-and-working-hours-in-ganttpro</link><generator>RSS for Node</generator><lastBuildDate>Fri, 13 Nov 2026 15:59:50 GMT</lastBuildDate><atom:link href="https://community.ganttpro.com/topic/103.rss" rel="self" type="application/rss+xml"/><pubDate>Mon, 26 Oct 2026 09:13:40 GMT</pubDate><ttl>60</ttl><item><title><![CDATA[Reply to Working days, weekends, and working hours in GanttPRO on Mon, 26 Oct 2026 09:33:46 GMT]]></title><description><![CDATA[<p dir="auto">Hi Emily! Yes, you can absolutely customize the working schedule for a project in GanttPRO.</p>
<p dir="auto">Go to <strong>Project settings =&gt; Change working week</strong>. This setting will let you choose the working days, hours, add days off, holidays, and custom days.<br />
You can also save a configured project calendar as a template and reuse it in future projects!</p>