<?xml version="1.0" encoding="UTF-8"?><rss xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:content="http://purl.org/rss/1.0/modules/content/" xmlns:atom="http://www.w3.org/2005/Atom" version="2.0"><channel><title><![CDATA[Adding delays or overlaps between dependent tasks in GanttPRO]]></title><description><![CDATA[<p dir="auto">Hello! I'm working on an office renovation project in which some tasks require a waiting period before the next one can begin. Often, for example, we need to allow time for materials to dry before moving on to the next construction stage. In a different scenario, as some activities can run in parallel, the next task should start before the previous one is fully completed.</p>
<p dir="auto">How can I add delays or overlaps between dependent tasks in GanttPRO without breaking the existing dependencies? Will these adjustments still work with Auto Scheduling enabled? Thanks!</p>
]]></description><link>https://community.ganttpro.com/topic/105/adding-delays-or-overlaps-between-dependent-tasks-in-ganttpro</link><generator>RSS for Node</generator><lastBuildDate>Fri, 13 Nov 2026 15:43:52 GMT</lastBuildDate><atom:link href="https://community.ganttpro.com/topic/105.rss" rel="self" type="application/rss+xml"/><pubDate>Fri, 30 Oct 2026 11:01:18 GMT</pubDate><ttl>60</ttl><item><title><![CDATA[Reply to Adding delays or overlaps between dependent tasks in GanttPRO on Fri, 30 Oct 2026 11:35:16 GMT]]></title><description><![CDATA[<p dir="auto">Hi! You can manage this using lag and lead time in GanttPRO :)</p>
<p dir="auto">Click on the dependency line connecting two tasks. In the dependency settings, you'll find the option to set the required lag or lead time.<br />
Lag (+): adds a delay between dependent tasks. For example, +2 days creates a two-day gap.<br />
Lead (-): creates an overlap, allowing the following task to begin before the preceding task finishes.</p>
<p dir="auto">These settings also work with Auto Scheduling enabled. If connected tasks move on the timeline, GanttPRO preserves the configured lag or lead time.<br />
The time units depend on the Duration step configured for your project.</p>
<p dir="auto">Hope this helps!</p>