How to compare planned and actual project schedules in GanttPRO using baselines
In our work, we have very fast changing deadlines and task durations, so I’d like to be able to compare the current schedule and the original plan. Also, understand the shifted tasks and how great of an impact those changes have. Is it possible to create a baseline when the project has already started? Also, I’d like to save it and compare it with the current schedule.
Comments (1)
Hi Lucas! Yes, GanttPRO's Baseline feature will help you compare the current version with a previously saved one.
How to create one: in the upper-left corner, click the Baseline icon and select Create baseline. You can rename it how you want later to better identify.
When you select a saved baseline, black bars appear beneath the tasks on your Gantt chart, showing their original positions. To identify the changes, you can compare them with the current schedule.
There is no limitation in the saved number of baseline but only one can be displayed at a time. Additionally, you can also use History of changes when your project has already started. Just select an earlier version and save as a baseline.