How to add holidays and non-working days in GanttPRO?
Is it possible to add holidays and non-working days in GanttPRO’s project calendar? I’d like the project schedule to exclude public holidays, company days off, or other dates when no work should be planned.
Also, it would be great if they repeated automatically every year.
Thanks
Comments (1)
Hi Adrien! Yes, it is currently available in GanttPRO’s Project calendar.
Where you can find it: go to Project settings => Change working week, then add an exception as a Day off. There you can add a name of the holiday/day off, select a date, set it as recurring, choose whether it should repeat indefinitely or until a specific date.
Also, if you need a non-standard working schedule instead of a full day off, you can add the Custom days. For instance, 4 hours instead of 8. GanttPRO takes these calendar settings into account when scheduling tasks, and full non-working days are shown in gray in the Calendar view.
All customized calendars can be saved at templates as well!